ADB TA-8791: Second Green Power Development Project

ADB TA-8791: Second Green Power Development Project
Client

Druk Green Power Corporation (DGPC) and ADB

Location

Bhutan

Duration

July 2015 – December 2016

Services provided

Environmental and Social Safeguards

This CDTA undertook a review of sector reforms, policy/act review, and investment and financing strategy of DGPC, alongside institutional capacity building, and revised the environmental and social assessment documentation for the Tangsibji Hydropower Project.

Outcomes

We delivered the following solutions to ensure compliance:

  • Served as JV partner with PwC, providing a team of four local consultants — Electrical Engineer, Socio-Economic Consultant, Environmental Consultant, and Communications and Media Consultant.
  • Established the Biodiversity Committee and prepared ToRs and MoUs for biodiversity surveys with the National Biodiversity Centre.
  • Developed protocols and formats for the environment management plan.
  • Assisted with implementation and monitoring of the Resettlement Plan and community development programmes.